Posted By Topic: Adding to existing PV system

Phazor
Sep 06 2017 12:04

Existing string inverter system inspected and registered on the High Risk data base. Adding 4 extra modules to the second tracker on inverter. Still within inverter's specs OK.
Does the extra modules need to be inspected and another High Risk Data job logged for this site
   

zl2aj
Sep 06 2017 12:49

I cant see this as being "repairs and maintenance" - its better described as additions / alterations. Because it is PV this would make it high risk = inspector.
   

Sarmajor
Sep 06 2017 13:01

Installation of additional equipment to PV = high risk.
Requires inspection and a new ROI. Also new record in the EGHRD.